One of our properties in the UK is on the way of becoming inhabitable

Most recent developments in week 3 and 4.

Lots of plastering underway, starting at the top of the house and working down. Started to remove render off the back, that will be a focus this week. New walls on top floor where brick wall taken out. Red wires are where the electrician has started putting the full fire alarm and smart fence lighting system in.

Solid progress with next wall taken out. New wall and new floor on top floor, good progress on plastering. Less progress externally as renderers have been delayed but should be working over the weekend.